Monday, 9 July 2012

CS615 VU Current GDB No. 1 Spring 2012 Solution

Starting Date Monday, July 09, 2012
Closing Date Tuesday, July 10, 2012

Question/Description
Below is the topic for GDB. As you have learnt about Work Breakdown Structure (WBS) in this course, on the basis of your knowledge, can WBS be considered as a plan/schedule? Justify your answer with solid reasons.

Solution:
you can read the complete idea page number 241. WBS is related to planning and scheduling a project.
Work Breakdown Structures (WBS)
Do not and cannot drive any processes
Must model the processes used by the environment
Is not a schedule
Are DELIVERABLE based NOT activity based
according to this “it is not a schedule”
Answer will be that wbs is not a schedule.
Read page 249 0f lecture notes it says :-
WBS IS NOT:
1. A SINGLE document that substitutes for the project schedule or project plan
2.the project schedule
page 243
it’s not a single document that can be mistaken for the project plan, schedule or scope statement

No comments:

Post a Comment